Discover the new construction and conversion of the Käferschule with insights into the planning, contractors and interesting details such as the planned photovoltaic system. ">Discover the new construction and conversion of the Käferschule with insights into the planning, contractors and interesting details such as the planned photovoltaic system. ">

  • en
    • en
    • de
Filter Tags
Filter Tags
  • Internal pages
  • News
  • Documents (PDF)
  • External pages
  • All results
search

Käferschule - New building & Conversion

Beetle School
  • Profile

    Start of construction: spring 2022

    Expectedcompletion of new construction: Summer 2023

    Estimated completion ofremodeling: Summer 2024

    Total costs: 7.000.000 Euro

  • Planner

    Architect: Wob Consult (current)

    Structural engineer: LepkeIngenieurgesellschaft mbH&Co

    Soil expertise: Gesellschaft für Grundbau und Umwelttechnik

    Fire protection: IFB Schütte, Brandschutzberatung Kröger GmbH

    Electrical engineering: IB Schulz Ingenieurbüro

    Heating-Ventilation-Sanitary: INGENIEURBÜRO MEYER

    Kitchen planning: Scholz Planungsbüro für innovative commercial kitchens

    Acoustics: GTA -Gesellschaft für Technische Akustik mbH

    Outdoor facilities: Prisma Digital As-built survey,

    pro garten landscape architectsBresser Jablonka PartGmbB

    SiGeKo: IUP.engineers

    Building surveying: Vermessungsbüro Stein und

  • Executing companies

    Shell construction: PARTNER BAU Quedlinburg GmbH

    Roofers: DachdeckereiMarco Schulze GmbH & Co. KG

    Scaffolding: Hibbeln GmbH

    Grounding and lightning protection: Wagener & Thormählen GmbH

    Power installation: Schröter Elektro-,

    Schalt- und Regeltechnik GmbH Hecklingen

    Light current installation: ABL GmbH & Co. KG

    Heating and plumbing: Spiller& Krüger GmbH & Co.KG

    Facade: GEBOthermGmbH,

    Thorsten Stielau carpentry and timber construction

    Metal construction and locksmith work: DaenickeStahl-Metallbau GmbH

    Screed: K B Böden GmbH

    Interior plaster: Weser BauputzGmbH

    Interior doors: Neiteler& Brand BauelemenetGmbH

    Cabinetmaker: Joinery Ludger Ostlinning

    Floor coverings: Company RAULFS GmbH,

    Tiles & Dry construction: Christian Noack


  • Description of the construction measure

    New construction, remodeling and expansion are planned until summer 2024.

    The project will be built in two construction phases from March of this year until probably July 2024. In the first stage, a new school building is to be constructed by July 2023. This will then be followed by the remodeling and expansion of the cafeteria from August 2023 to July 2024.

    The new building will contain six classrooms, four differentiation rooms and a therapy room for special offers. There will be a spacious hallway area with play niches in conjunction with large bay windows. There will be bright, friendly classrooms with decentralized ventilation systems, sun protection, modern IT equipment for digital learning opportunities. Special attention will be paid to accessibility in terms of room acoustics, elevator and automatic doors.

  • Interesting aspects

    There will be a photovoltaic system on the roof, which will serve as a contribution to climate protection and generate approximately 35,000 kWh of electricity per year. An information monitor in the break hall will illustrate the topic for children and parents.

    • The foundations are poured - 05.04.2022

      The foundations are poured - 05.04.2022

      1 | 15
    • The first walls are up - 03.06.2022

      The first walls are up - 03.06.2022

      2 | 15
    • The ceiling elements are mounted - 04.07.2022

      The ceiling elements are mounted - 04.07.2022

      3 | 15
    • The upper concrete ceiling is poured- 26.08.2022

      The upper concrete ceiling is poured- 26.08.2022

      4 | 15
    • Topping out ceremony - 22.09.2022

      Topping out ceremony - 22.09.2022

      5 | 15
    • The roof is sealed

      The roof is sealed

      6 | 15
    • The windows are installed - 17.11.2022

      The windows are installed - 17.11.2022

      7 | 15
    • Installation of ceilings and floors in a classroom - 06.06.2023

      8 | 15
    • Ceiling substructure in the break hall - 13.06.2023

      9 | 15
    • Ceiling substructure in the hallway - 22.06.2023

      10 | 15
    • Advanced ceiling work - 22.06.2023

      11 | 15
    • Classroom with cabinet niches - 23.06.2023

      12 | 15
    • Exterior view of the school building - 27.06.2023

      13 | 15
    • Exterior view of the school building - 29.06.2023

      14 | 15
    • The flooring is laid - 29.06.2023

      15 | 15
    By using this function, you agree that the data may also be transferred to third countries, outside the European Economic Area, without an adequate level of data protection (especially USA). It is possible that authorities may access the data without any legal remedy. You can revoke your consent at any time. Further information: Privacy policy