Summer construction sites
We renovate our roads for you

"In order to improve the condition of our roads, we have to put up with roadworks and road closures, unfortunately there is no other way. For our busiest roads, we also only have small windows of time each year that we want to use efficiently. As a result, we have a lot planned for the summer. Our colleagues on site are doing everything they can to keep the restrictions as low as possible," comments Kai-Uwe Hirschheide, First City Councillor and City Planning Officer.
During the plant vacations: Heinrich-Nordhoff-Straße and Braunschweiger Straße are being renovated
This summer, we are tackling the second construction phase on several streets where we already renovated the first last year. With Heinrich-Nordhoff-Straße - out of town, northern carriageway, between the junctions with Saarstraße and Lessingstraße - and Braunschweiger Straße - out of town, between the junctions with Siemensstraße and Röntgenstraße - this is the case on two central traffic axes. However, both roads will remain open and traffic will be routed in one lane on the other side of the road. In both cases, construction will take place during the plant vacations from July 7 to August 1.
In addition, the Willy-Brandt-Platz road will be completely closed in sections from June 10 to 20. We will announce the corresponding restrictions and detour in good time. A new asphalt surface course will also be laid on Schillerstraße. Between July 11 and 21, both directions of traffic between the junction with Heinrich-Heine-Straße and the junction / traffic lights at Schillerpassage are expected to be repaired. This will require a full road closure and the corresponding detour is currently being coordinated.
Further measures throughout the city
In addition to the central traffic axes in the city center, further measures are planned throughout the city. Construction work is underway in the following districts:
Mitte West: basic renewal of Sauerbruchstraße, construction starts on June 23, construction time around eight months, traffic will be maintained during the work
Ehmen: Mörser Straße road surface renovation, expected July 4 to 10
Hellwinkel: resurfacing of the Dahlienweg/Schreberstraße link road, July 4 to 11
City center: Repairs to ZOB bus platforms 2, 4 and 6, probably July 9 to 31
Fallersleben: Hofekamp road surface renovation, probably July 14 to 17
Kästorf: Pavement renovation Kohlgärten (K 46), probably July 14 to 17
Nordstadt: Werderstraße road surface renovation, probably July 14 to 17
Warmenau: K 46 road surface renovation, probably July 14 to 21
Warmenau: bridge deck renovation, probably July 14 to 21
City center: Joint renovation Porschestraße, expected July 14 to August 13
Wendschott: repair of Brechtorfer Straße, probably July 21 to 30
Barnstorf: K 111 surface treatment, probably August 4 to 8
Nordsteimke/Hehlingen: Alternative Green Route Section South 1, along the K 5 between Steimker Gärten and the Steinbeker Straße junction, expected from August, one lane of traffic in both directions
Brackstedt: Lange Trift footpath and cycle path renewal, construction period: mid-August to mid-September, half-lane closure of the carriageway in alternating traffic, full closure of the footpath
Neuhaus: Next section of basic renewal of Alexanderberg road. Construction period: from August 2024 to November 2025. Road is fully closed for the construction period, free for residents. Steinkopf bus stop will not be served.
Hellwinkel terraces: The final road development with the construction of sidewalks, parking pockets, tree islands and road surfacing will continue. Construction period: at least until the end of 2025. The work will be carried out in sections with full road closures.
For all measures, this is a planning status and changes are still possible. As soon as further, concrete information is available, the city administration will inform you as usual.